Caldwell Place Project to Begin with Test Pits, Road Closures Expected

SPRINGFIELD, NJ - Township officials have released updated details on the long-awaited Caldwell Place Project, a county-led effort that will replace the aging culvert and upgrade underground utilities between Mountain Avenue and Rose Avenue.
The project is set to begin with test pit work on Wednesday, September 3, 2025, which will require a temporary one-day closure of Caldwell Place. The test pits will help engineers assess the condition of the site and finalize plans for the first phase of construction.
If results are favorable, Phase One will follow from September 15 through September 26, 2025. During this stage:
-New Jersey American Water will replace both the 12-inch and 8-inch water lines.
-PSE&G will then relocate existing gas lines.
-The size and complexity of the trench required means the road will be fully closed for two to four weeks.
Future phases, which have not yet been scheduled, will involve the complete replacement of the Caldwell Place culvert by Union County. That work is expected to begin in the fall and take approximately three to four months to complete.
"The administration will be keeping a close eye on this project," township officials said in a statement. "We will continue to provide updates as they become available."
Residents are urged to monitor the township's website and social media for traffic advisories, detour information, and further scheduling updates as work progresses.